Implementing ERP

By Stuart van Rij | Thursday, October 15 2009

There are three often neglected areas to focus on before inking the deal.

ERP implementations are complex, expensive and prone to failure. As Thomas Wailgum notes, “ERP projects have only a 7 percent chance of coming in on time, most certainly will cost more than estimated, and very likely will deliver very unsatisfying results” (See “Why ERP is still so hard” ).

And yet, these ERP solutions still play an essential part in many businesses.

When embarking on an ERP implementation, there are all manner of issues and options that need to be worked through to reduce the risks. Set out below are three often neglected areas to focus on before inking the deal.

Where are the hidden licence costs?

History has proven that the potential for cost “blow out” in an ERP project is huge. And it’s not just the usual suspects of data conversion, change management and customisation. The complex, and sometimes peculiar, licence terms hide many provisions that can be used to “hook” additional licences down the track. It’s essential to get to grips with the detail and focus on the following sorts of issues:

  • How much flexibility is there to chop and change certain variables (for example licensed users, sites, business roles) to fit changing business needs with minimal, or at least predictable, financial impact?
  • To what extent can the software be accessed and used by affiliates, business partners and service providers. (For example will you need to pay additional licence fees if you enter into outsourcing arrangements down the track?)
  • Is it clear what “use” of the software actually permits and does this fit with your needs?

Is there a commitment to deliver the promised solution?

In accepting the implementer’s standard form contract (not ideal), you can expect few, if any, meaningful remedies, warranties or “skin in the game”. The overall warranty and liability regime will need some serious panel beating (See “Fine Print Finesse”).

However, the following areas should also be a focus:
  • Top notch project management plays a critical role in project success. Is the implementer’s project manager any good? Is he or she legally and practically “locked in” for the implementation?
  • To what extent is the implementation partner responsible for the end-to-end solution? (Check for integration between the software supplier and implementation partner contracts to avoid “finger pointing” scenarios.)
  • Is the baseline of requirements for the solution rock-solid? All manner of documentation can be exchanged in a large implementation. Care is needed to avoid your initial requirements being inappropriately superseded by the extensive project documentation. Don’t underestimate just how easily this can occur. The requirements baseline needs to be appropriately protected in the contract.

Are there realistic obligations on the team?

Successful implementation requires “boots and all” involvement from the customer. However, the last thing you want is an implementer that has failed to do their due diligence and made unrealistic assumptions as to your resources and capabilities. This has cost-overrun written all over it. Here are a few things to focus on:
  • Are the assumptions and customer obligations clear, understood and manageable?

n What will take place when the customer fails to perform or an assumption proves to be invalid? At least make sure the implementer is required to raise issues immediately (so they can be addressed and don’t fester) and there’s an agreed regime for managing the downstream impact on cost and liability.
  • To what extent should the implementer be prevented from re-pricing or wriggling out of liability, if it transpires that its due diligence has been inadequate?
  • Should the implementer be obligated to “hand hold” the customer throughout the project, providing all necessary guidance and assistance?

No one can guarantee a successful ERP implementation. However, addressing these types of issues at the beginning of a project will reduce the risk of being caught out at the tail end.

Stuart van Rij is a senior associate at Wigley & Company, a law firm specialising in ICT. He can be reached at (04) 4991842 or stuart.vanrij at wigleylaw.com.
news

events

MIS100 Event 2010
Presenting the MIS100, the annual report on the top IT users in New Zealand
To read MIS100 2010 report, click here
For the speakers' presentations, click here
Sponsor: Microsoft Services, Gentrack

CIO Awards 2010
» CIO of the Year Award
  Sponsored by: NetApp

» Excellence in IT Recruitment Award
  Sponsored by: ITCRA

Closing date for submissions is Thursday, 24 June 2010.

2010 CIO Summit
Date20 & 21 July 2010
For more information about the CIO SUMMIT 2010, click here

MIS100 2010MIS Strategic 100 Business Software Guide 2008

- CIO Insider
- CIO News Round-Up

Get the latest news from CIO delivered via email.

signup now

Subscribe

CIO is bringing together the best of MIS NZ and CIO, the new look CIO is the only magazine that focuses on the unique management needs of senior IT professionals.

subscribe now